MANUFACTURING FAILURE
Approved, then changed
A motor mount plate was reviewed and approved on Monday. On Tuesday, the designer moved two holes 4 mm for a new motor. The approval stayed on the drawing, and the release went out Wednesday.
Cost: 260 plates cut with holes in the new location that no one had reviewed. Twelve interfered with a frame rib and were scrapped, and the rest needed a fit check.
How Preflight catches it: MB-013 needs a named geometry confirmation, and that confirmation goes stale as soon as the requirements or geometry change.